Smore logo
remove_red_eye 38
page background

Montclair Public Schools

September 16, 2024

Montclair Public Schools  September 16, 2024
MontclairPublic Schools September 16, 2024

Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

Renaissance @ Rand Renaissance @ Rand

Project Status: November 21, 2025

Project Completion: 50% complete

Current Status: New boiler has been running for approximately one week. Prepping to demolish 2nd existing boiler

Upcoming Milestones: Begin demolition of 2nd existing boiler.

Contract to Date: $3,785,100.00
Paid to Date: $845,451.88

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: November 21, 2025

Project Completion: 52% complete.

Current Status: Demolition of 2nd existing boiler is under way

Upcoming Milestones: Build 2nd new boiler

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Bradford Elementary Bradford Elementary

Project Status: November 21, 2025

Project Completion: 51% complete.

Current Status: New boiler has been running for approximately one week. Prepping to demolish 2nd existing boiler

Upcoming Milestones: Begin demolition of 2nd existing boiler

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Watchung Elementary Watchung Elementary

Project Status: November 21, 2025

Project Completion: 51% complete.

Current Status: New boiler has been running for approximately one week. Prepping to demolish 2nd existing boiler

Upcoming Milestones: Begin demolition of 2nd existing boiler

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Edgemont Elementary Edgemont Elementary

Project Status: November 21, 2025

Project Completion: 50% complete.

Current Status: New boiler has been running for approximately one week. Prepping to demolish 2nd existing boiler

Upcoming Milestones: Begin demolition of 2nd existing boiler

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Northeast Elementary Northeast Elementary

Project Status: November 21, 2025

Project Completion: 50% complete.

Current Status: New boiler has been running for approximately one week. Prepping to demolish 2nd existing boiler

Upcoming Milestones: Begin demolition of 2nd existing boiler.

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter