SHANNON ES - MPR Project
March 2026

Project Updates - March 2026
Activities This Month
Complete fencing and gates
Complete trash enclosure
Punch list for the cafeteria and stage
Remove temporary fencing and open up the site for full use (excluding the kitchen)
Develop a punch list for site work and the kitchen
Activities Next Month
- Health department inspection for the kitchen
- Complete irrigation
- Punchlist work
Project Overview
Project Scope: This project will include the construction of a new multipurpose building featuring a dining area, stage, food services kitchen, serving areas, and support spaces—an investment in our community using taxpayer-funded bond dollars.
Upon completion, the existing portable cafeteria will be removed. The project also includes roll-up doors for exterior access, surrounding landscaping, and infrastructure for a new garden.
Anticipated Completion: Spring/Summer 2026