DCSC Construction Update

Update #26

DCSC ConstructionUpdateUpdate #26

August 2026 August 2026

School may not have been in session, but the DCSC campus was still bustling with activity this summer! Our new transportation building is officially complete, the high school made a TON of progress, and the new administration building addition is moving through all the right phases.


In fact, there isn’t a single building on our campus that didn’t see some sort of improvement while we were away! We can’t wait to see all of these projects come together as we continue Building a Successful Future.


Keep reading for more detailed updates and photos of our progress!

High School Progress High School Progress

Over the summer, our crews completed (or nearly completed) the Family and Consumer Science (FACS) space, the new business suite, the temporary cafeteria, a new art space, the planetarium, and a few other spaces (including most of the main gym renovation and new life skills space - both of which will be completed very soon!). They are now moving onto the greenhouse, cafeteria, auditorium, and other various corridors throughout the building. Even some of the "completed" spaces will continue to see additional design work and small improvements as the year goes on!

User uploaded image
zoom_out_map

Greenhouse

The greenhouse is another space that has remained largely untouched for years. This renovation will give students more room to learn, grow, and work in a space that’s updated to better meet their needs. Looks like future plant sales could be bigger and better than ever!

User uploaded image
zoom_out_map

Cafeteria

The cafeteria everyone knew and loved is officially under construction! In the photo above, crews are working on the underground electrical as the renovation gets underway. When complete, the space will feature a more modern design, additional seating, and a much more efficient layout. We can’t wait to see this space come together!

User uploaded image
zoom_out_map

Main Gym

The new and improved main gym is coming along nicely! The renovation will bring new flooring, a new projector, and a more modern, updated space for our athletes to call home. We can’t wait to see the finished product!
User uploaded image
zoom_out_map

Auditorium

The auditorium saw plenty of progress this summer, including new lighting and duct work! This space needs quite a few smaller updates, and crews are working through them in a way that minimizes disruptions for our performers.

While most of the renovations will pause for now, the auditorium will close down again next summer for additional work and will be ready for action when the new school year begins!

User uploaded image
zoom_out_map

Planetarium

Who remembers this space from when they were a kid?! Danville is incredibly fortunate to have such a unique and innovative space where students can learn, explore, and discover. Over the years, though, the chairs had started to fall apart, and the room needed several cosmetic and safety updates. This summer, our crews brought the space back to life, and it’s now ready to welcome another generation of eager astronomers!

User uploaded image
zoom_out_map

FACS

This space now features an Early Childhood Development classroom, a new Culinary Arts professional lab, a foods lab, and another FACS classroom! Much of the equipment in the old space was outdated, and the classrooms were becoming too small to comfortably accommodate the number of students enrolled. Now, the space is larger, more modern, and equipped with tools that meet current industry standards. These updates will give our students more room to learn and hands-on experiences that better prepare them for opportunities beyond the classroom!

Transportation Transportation

Our new Transportation Building is COMPLETE!!! This new space provides much-needed additional office space, gives our bus drivers a dedicated area for large-group training and a place to sit between routes, and provides our mechanics with updated space and tools for repairs. The project also includes a safer, more efficient bus lot and gives our Transportation Department the updated facility they have long deserved! We are so happy with the results and can’t wait to see our drivers and mechanics continue to make the most of this incredible new space!

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Administration Building Administration Building

If you’ve passed by the Administration Building lately, you’ve probably seen what looks like a whole new building! Right now, crews are working on the addition, which includes office and meeting space (including a new board room) built onto the current structure.


As shown in the photos below, the current building will remain, with some light interior upgrades to improve its function. The new addition will include several new offices, allowing us to bring more administrative staff together under one roof. This will ultimately free up space for students in our school buildings and strengthen collaboration across our entire administrative team.


We are so excited to see this project take shape!

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Follow us to learn more!

This blog post, as well as other information (videos, photos, etc.), can all be found on our website and social media. Be sure to follow us to see what is happening now and what is happening next!

Email: aengland@danville.k12.in.us
Website: https://www.danville.k12.in.us/
Phone: 317-745-2212
Facebook: https://www.facebook.com/DCSCWarriors
Twitter: @DCSCWarriors

DCSC Warriors
DCSC is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter