Cameron ES Critical Needs Project
August 2023

Project Updates - August 2023
Construction Completed Last Month
- Painting of the mechanical ductwork
- Completion of the equipment enclosure
- New asphalt at the drop-off area
- Installed new accessible door hardware
Upcoming Activities
- HVAC equipment start-up and commissioning
- Floor preparation and installation of the new hallway flooring
- Installation of metal shroud around refrigerant piping
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Winter 2023
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Accessible Restroom
Accessories installed in the revamped student restroom
Door Hardware
New accessible door levers and locks