Activities This Month

  • Fabricate structural steel at the shop for the south side
  • Erect structural steel on the north side
User uploaded image
zoom_out_map

Activities Next Month

  • Continue erecting structural steel on the south side
  • Install metal deck on the north side
User uploaded image
zoom_out_map Show in original size

Project Overview Project Overview

The Richmond High School Modernization project involves demolishing a portion of the classroom building to make way for a new two-story building along 23rd Street. The remaining classroom section will be updated, including the installation of new windows. The large gym and the 600 buildings will receive a refresh.

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.



Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
RHS Modernization Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by