May 4, 2026
Bond Update
SUMMER SCHEDULE RAMPING UP ๐
๐ช๐๐จ
Many Projects Coming Online!๐ฎ
This spring and summer, Mattawan Consolidated School will advance with major components of our ongoing $110M school construction bond project!
๐During the summer of 2026 we will partner with Great Lakes Furniture Supply to install new furniture at both the middle school and high schoolโincluding new teacher workstations, key program supports (choir risers/chairs, music stands, robotics/STEM workstations), and a substantial refresh of high school student classroom furnitureโcompleted under budget so building leaders could secure all identified high-priority items.
๐Phase 1 of Bid Package 1B (Traffic Flow) will be underway this spring. This will involved the construction of a new bus lane southside of the middle/high school as well as an access drive between the middle school and ball diamonds. The entire project came in about $200,000 under the $6.2M budget at $5.9M. Phase 2 is scheduled for summer 2027 and will address parking and carpool/traffic flow on the North side of the middle and high schools.
๐Construction progress continues on the new Transportation & Maintenance Facility, with work moving forward again this summer.
๐Phase two of our stadium enhancement scheduled to begin in the Summer of 2026, will include the addition of a new sound system, as well as the completion of the home bleacher facing (top portion).
๐Construction documents will wrap up this June for the New Cafeteria and Main Office project at the middle school. The projects will go out for bid after this!
ON-GOING PROJECTS ๐
๐BID PACKAGE 1B PAVING THE WAY!๐
Phase 1 of BP1B Ushers in Access Drive and New Bus Lanes ๐
Latest Update
Recent progress includes continued material deliveries, staging, and preparation for storm-related work. Crews also removed the utility supply box and post and replaced an irrigation line that had been hit. Looking ahead to next week, work will continue on miscellaneous storm items, sidewalk preparation will begin near the baseball and softball areas, and pre-cast bases have been ordered with installation to be determined.
Other Information/Reminders
Bid Package 1B carried an overall budget of $6.2 million, with the selected bid coming in approximately $200,000 under budget at $5.9 million. The work will be completed in two phases: Phase 1 will begin and be completed during the summer of 2026, with Phase 2 scheduled for the summer of 2027.
Planning accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:
- Fully separate buses from carpool and staff traffic at both the middle and high schools
- Reconfigure the carpool traffic routes at both the middle and high schools
- Add needed parking in front of middle and high schools
- Add a through drive east to west for bus traffic to move within our district
- Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow
- NOTE: the removal of 4 current tennis courts will be needed to facilitate the bus lane behind the building due to grade and utilities limitations. As a reminder, 12 new courts will be constructed south of the stadium in bid package 4.
BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION๐
New Updates! ๐๐๐ซ๐
Recent work on the project continues to move forward, with several important site and building components advancing. Roof panels are nearing completion on the lower administrative portion of the building, and purlin bracing installation is underway in that same roof area. Underground electrical work has also started, marking continued progress on the buildingโs infrastructure systems.
Site concrete preparation is also progressing. Crews have been preparing for the concrete spillways and the dumpster pad, and bollards have now been installed at the dumpster pad area.
Looking ahead, the roof installation on the lower administrative portion of the building is expected to be completed. Underground electrical rough-ins will continue, and underground plumbing work is scheduled to begin. Crews also anticipate pouring the concrete spillways and the concrete dumpster pad as site work continues to advance.
Archived BP 2A Information
Bid Package 2A - Site Work & Prep ๐ข๐๐ง
Did you know?
Current Maintenance Building will be demolished to make room for Natatorium/Field House
Current Bus Barn will be maintained as a district storage facility
New building will serve as primary hub for both maintenance and transportation departments
Total Square Footage of new building: 24,554 sq ft
Building Highlights:
4 drive through bus maintenance bays
Dedicated parts room, wood shop and machine shop
Dedicated, dehumidified district storage
Locker rooms
Kitchen
Training room/lounge
4 offices with additional workstations for secretaries and maintenance staff
Building Receiving Loading Dock
40 exterior bus parking spots
Secured employee parking
Exterior salt storage
General Information
Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker-and-shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.
This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.
Tree Removal/Replacement & Disc Golf Course
The disc golf course on the west side of the high school was recently removed to prepare for construction of the new transportation and maintenance facility, slated to begin this winter. Approximately nine baskets and several trees were removed, a step the district did not take lightly. We recognize how meaningful this wooded space and recreational area have been for students and neighbors, and we share the disappointment that comes with altering a natural setting. Our team is working carefully to limit environmental impact and is committed to thoughtful tree replacement as part of the project. We are also exploring possibilities for relocating the disc golf courseโpotentially off campusโso the community can continue to enjoy the game in a new setting.
Classroom Furniture Update๐ช๐ซ
Installation set for Summer of 26! ๐ช๐ซ๐
Click on the link below for more details.
ARCHIVED INFORMATION
Construction Bid Packages Explained
Our Plan. Our Students. Our Future.
Construction Bid Packages Explained
The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.
2024
Summer 2024
โ COMPLETE Owner Direct โ Replace Existing Soccer Lights
โ COMPLETE Owner Direct โ Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)
Fall 2024
โ COMPLETE Owner Direct โ Student Device Replacement Phase 1
Winter 2025
โ COMPLETE Owner Direct โ Student Device Replacement Phase 2
2025
March โ August 2025
โ COMPLETE - Bid Package 1A โ Football Stadium: Inner Scope
Summer 2025
โ COMPLETE- Bid Package 1C โ Baseball & Softball Field Improvements
โ COMPLETE Bid Package 1D โ HS Replace Fire Alarm System
โ COMPLETE Bid Package 1E โ HS Carpet Replacement
Fall 2025
โ UNDERWAY- Bid Package 1F โ HS Gymnasium Cooling
โ SOURCING MATERIALS Owner Direct โ Auditorium (Band Shell, Pit Section, Lighting, Stage Floor, A/V, Curtain)
Nov 2025 โ Oct 2026
โ UNDERWAY Bid Package 2 โ Transportation & Maintenance Facility
2026
March โ September 2026
โ PROJECT UNDERWAY - Bid Package 1B โ Campus Traffic Flow
Sept 2026 โ March 2028
โ DESIGN PHASE UNDERWAY - Bid Package 4 โ Field House
โ DESIGN PHASE UNDERWAY - Bid Package 4 โ Natatorium
โ Owner Direct โ SOURCING MATERIALS: Summer 2026
2027
Summer 2027
Bid Package 3 โ MS Upgrade Domestic Water Heaters
Bid Package 3 โ MS Replace Fire Alarm System
Bid Package 3 โ MS Replace Building Temperature Controls
Bid Package 3 โ MS Replace Chiller & Associated Pumps
Bid Package 3 โ MS Replace Boiler & Associated Pumps
Bid Package 3 โ MS Add 3rd Boiler for Redundancy
Bid Package 3 โ MS Classroom Wing Security Doors
Bid Package 6 โ Upgrade Domestic Water Heaters
Bid Package 6 โ Upgrade ECEC Gym AHUs to Include Cooling
March โ August 2027
Bid Package 4 โ Tennis Court Facility
June 2026 โ August 2027 (overlapping start)
DESIGN PHASE - Bid Package 3 โ MS Cafeteria Renovation
Sept 2027 โ March 2028
Bid Package 6 โ HS Weight Room Addition
2028
March โ August 2028
Bid Package 6 โ HS Locker Room Renovation
June 2026 โ August 2028 (overlapping start)
DESIGN PHASE - Bid Package 3 โ MS Front Office Expansion
Summer 2028
Bid Package 1B โ Stadium Press Box Upgrades
Bid Package 5 โ MS Replace Interior Lighting to LED
Bid Package 5 โ MS Replace Ceiling Tiles (with Lighting Replacement)
Bid Package 5 โ MS Replace Corridor Lockers
Bid Package 5 โ MS Renovate Science Labs (6th & 7th Grade)
Bid Package 5 โ MS Renovate Toilet Rooms
Bid Package 6 โ HS Auditorium Exterior Upgrades
Bid Package 6 โ HS Exterior Masonry Upgrades (@Entry Canopies)
Bid Package 6 โ HS Replace Interior Lighting to LED
Bid Package 6 โ HS Renovate Toilet Rooms
Bid Package 6 โ HS Renovate Science Labs
Bid Package 6 โ HS Replace Building Temperature Controls
Bid Package 7 โ Practice Fields
Bid Package 7 โ Baseball & Softball Upgrades
March โ August 2028
TBD โ Multipurpose/Soccer Competition Field
TBD
Owner Direct โ Replace Security Cameras
Owner Direct โ Technology District Wide: Classroom Upgrades
Owner Direct โ Technology District Wide: Large Spaces (Gymnasium A/V)
Bid Package 7 โ Football Stadium: Outer Scope / Entry
Additional bus purchasing
Our focus revolves around five key objectives for the bond:
- Preserve existing assets
- Prioritize safety and security
- Provide future-focused academic and extracurricular experiences for our students
- Enhance infrastructure
- Demonstrate fiscal responsibility
Safety & Security:
- Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
- Replacement of outdated, unreliable security equipment at each building
Transportation:
- Continued replacement of an aging bus fleet
Academic Learning Spaces + Experience:
- Replacement of original, aged classroom equipment and furniture at middle and high schools
- Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.
Fine Arts:
- Upgrades to lighting and media equipment at the high school auditorium
Infrastructure:
- Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
- Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
- Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
- Addition of cooling to main gymnasiums at the high school
Student Athletic Experience:
- Renovation of aged high school locker rooms
- Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
- New high school track - the current track is backwards and nearly unusable in the current condition
- Upgrades to baseball and softball fields
- Construction of a new multi-use turf field (soccer, lacrosse, football)
- Maintenance of existing practice fields; addition of a new outdoor practice space
Other Construction:
- Addressing overcrowding in the current Middle School cafeteria
- Replacement of aged, quickly deteriorating tennis courts
- Replacement of aged transportation building and maintenance building
- Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
- Construction of a student/community pool