Smore logo
remove_red_eye 480
page background
Logo

DCSC Construction Update

Update #23

DCSC ConstructionUpdateUpdate #23

January 2026 January 2026

Happy New Year! We hope everyone had a wonderful and refreshing break. While students and staff were away, our construction crews were busy making major progress at DCHS, the new transportation site, and the administration building—and the results are exciting!


Keep reading for more detailed updates and photos of our progress!

High School Progress High School Progress

Winter break brought significant progress across our high school building. Most notably, a wing of newly renovated classrooms was completed, along with extensive furniture movement to ensure students return to comfortable, functional learning spaces. Like our other newly updated classrooms, these spaces feature enhanced technology and tools designed to support both students and teachers.


Another area quickly coming to life is the broadcasting studio. In the photo below, you’ll notice the newly installed storefront windows, but this space has even more in store. In the coming weeks, the studio will include a greenroom and dedicated area for collaboration and editing, creating exciting opportunities for student creativity and learning.


Our band and choir rooms also saw major advancements over break. Both rooms are nearly ready for a final cleaning, then teachers can begin moving into the area. We can’t wait for our music students to experience and enjoy this upgraded space.


These updates are just a few examples of the exciting transformations happening throughout the school. The coffee shop, PLTW room, and media center are making tremendous progress, with work on the cafeteria and common spaces beginning soon. We look forward to sharing even more updates as these spaces continue to take shape!

User uploaded image
zoom_out_map

Classrooms

User uploaded image
zoom_out_map

Broadcasting Room

User uploaded image
zoom_out_map

Band Room

Transportation Transportation

If you’ve driven past the new transportation site recently, you’ve probably noticed the exciting progress taking shape. As with most construction projects, work began with the essentials, starting with framing and insulation.


Over the past month, crews have completed:

  • Insulation

  • Overhead MEP (mechanical, electrical, plumbing) installation

  • Window framing

  • Interior wall framing and layout

  • And more!


In the bottom photo, you can see the overall progress so far. This new facility will be an incredible upgrade and a much-needed improvement for our transportation team, and we’re excited to watch it continue to come together.

User uploaded image
zoom_out_map

Insulation and Framing Wall Layout

User uploaded image
zoom_out_map

Window Framing

User uploaded image
zoom_out_map

Overhead MEP

User uploaded image
zoom_out_map Show in original size

Administration Building Administration Building

If you’ve passed by the Administration Building lately, you’ve probably noticed the early stages of construction taking shape. We’re excited to share that this project marks the beginning of a significant expansion and renovation of our central office building. The updated space will include additional offices and a brand-new board room to support our monthly School Board Meetings.


As shown in the photos below, the current building will remain, with some light interior upgrades to improve its function. The new addition will include several new offices, allowing us to bring more administrative staff together under one roof. This will ultimately free up space for students in our school buildings and strengthen collaboration across our entire administrative team.


We are so excited to see this project take shape!

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Follow us to learn more!

This blog post, as well as other information (videos, photos, etc.), can all be found on our website and social media. Be sure to follow us to see what is happening now and what is happening next!

Email: aengland@danville.k12.in.us
Website: https://www.danville.k12.in.us/
Phone: 317-745-2212
Facebook: https://www.facebook.com/DCSCWarriors
Twitter: @DCSCWarriors

DCSC Warriors
DCSC is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter