Bricks and Mortar: 02/27/2026

BRICKS AND MORTAR
Bricks and Mortar Update: Board of Education Special Meeting, February 23, 2026 Summary
A meeting summary for Weston residents prepared by the Board of Education Communications Committee.
Background
The Weston Board of Education (BOE) is holding special monthly meetings from December 2025 until June 2026 to plan how to update Weston Public Schools’ (District) campus.
At the February 23, 2026 meeting, members of architecture firm SLAM Collaborative (SLAM) presented their Phase II investigation, which compared two options:
- Renovate the existing middle school.
- Build a new middle school.
To learn more, you can watch the meeting here.
Where We’ve Been So Far
Education Specifications
In May 2024, the BOE developed and approved Educational Specifications (Ed Specs), which is a written plan for what the renovated or new middle school should include.
State Reimbursement Process
At the December 1, 2025 special meeting, SLAM and other professionals explained how the state grant process works in order to receive state reimbursement for school construction. SLAM also reviewed major reports on school facilities since 2017.
Town and District Capital Improvements
First Selectwoman Samantha Nestor joined the January 7, 2026 special meeting to share information about the Town’s capital projects, and the District administration presented its 10-year capital improvement plan for other campus needs in addition to the middle school.
Grade Configurations
At the January 7, 2026 special meeting, BOE members asked the District administration to consider the educational impact of various grade configurations housed within a school. District administration presented a comparative analysis of grade configuration models at the February 2, 2026 general meeting.
Previous Bricks and Mortar Summary
Read the summary of the December 1, 2025 and January 7, 2026 meetings.
All Campus Revitalization Information Gathered to Date
Visit the Campus Revitalization section of the District website to see all prior studies, meetings, presentations, and newsletters.
What We Learned at the Meeting
Educational Specifications
SLAM used the Ed Specs to guide the Phase II investigation and confirmed:
● The number and size of rooms seem appropriate.
● The plan reflects a modern, 21st-century middle school design.
Option 1: Renovate as New
● How Would Renovation Work?
○ Students would stay in the building during three phases of construction.
○ During each phase, certain classrooms would relocate to portable classrooms that remain onsite during the entire project while a part of the building is renovated.
● Renovation Timeline
○ Active construction lasts at least three years.
● Slam’s Preliminary Opinion of Probable Renovation Cost (Starting Point for Discussion)
○ Total project cost: $134.5 – $141.4 million
○ Estimated cost to Weston after state reimbursement: $118.8 – $124.5 million
Option 2: Build a New School
● How Would Construction Work?
○ Students stay in the current building during construction.
○ After completion, students move into the new school.
○ The old building is then demolished.
● Construction Timeline
○ Active construction lasts about twenty-two months.
● Slam’s Preliminary Opinion of Probable New Build Cost (Starting Point for Discussion)
○ Total project cost: $136.1 – $143.0 million
○ Estimated cost to Weston after state reimbursement: $128.0 – $134.2 million
Additional Notes
- Estimated project costs assume eligibility factor of 0.8049.
○ Eligibility factor determines how much money the state will reimburse.
○ The closer the eligibility factor is to 1.0, the higher the state reimbursement.
○ 0.80 is typical for a school of our size.
- Project costs depend on the schedule. If the project is delayed, construction costs increase over time.
What’s Next?
- SLAM recommends that BOE members review the Ed Specs.
- Next BOE Special Meeting Monday, March 2, 2026 at 7 PM. Agenda item: School Facilities and Campus Revitalization – BOE member discussion including questions, perspectives, consensus building with focus on SLAM Phase 2 Report, next steps, strategies to address affordability.
- BOE members will continue discussing potential grade configuration changes.