Stege Rebuild Project
September 2026

September 2026 - Project Updates
Activities This Month
- Finished backfilling fuel tank excavations
- Completed lime/cement treatment at building pads
- Certify building pads (verification that design standards are met e.g. elevations, compaction, etc.)
- Begin rough grading at drive isles and play area
- Install main line underground electrical
- Start utilities in the public right of way
- Receive bids and finalize contract for Phase 2 construction
Activities Next Month
- Finish rough grading site
- Lime treat soil at remaining site (e.g. drive isles, play areas, etc.)
- Pending Board approval proceed with Phase 2 review and approval of submittals and material procurement
- Survey staking and layout for new buildings
- Begin excavating building footings
Project Summary
The Stege campus rebuild will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23