October 2024

Project Updates - October 2024
Construction Completed Last Month
- Installed waterproofing at footings and parapet flashing
- Installed exterior doors and windows
- Set piers and poured canopy foundations
- Began framing large canopies
- Began installing casework
- Began irrigation lines and sidewalks
Construction Work Planned for This Month
- Complete framing at large canopies
- Rough in electrical at HS and MS canopies
- Start up HVAC units
- Install casework countertops and sinks
- Install tack boards and marker boards
- Complete flooring
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Fall / Winter 2024
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net