SHANNON ES - MPR Project

November 2025

SHANNON ES - MPR Project November 2025
SHANNON ES- MPR ProjectNovember 2025

Project Updates - November 2025 Project Updates - November 2025

User uploaded image
zoom_out_map

Activities This Month

  • Installation of all electrical, mechanical and plumbing fixtures is complete.
  • The new floors were completed, including epoxy flooring, polishing the concrete and wood flooring on stage.
  • New wall paneling has been installed in the dining area.

Activities Next Month

  • Finish installing the kitchen equipment

  • Final coat of interior paint

  • Install window coverings

  • Install new concrete sidewalks

  • New asphalt paving for the fire road and service entrance

Project Overview Project Overview

Project Scope: This project will construct a new multi-purpose building featuring a dining area, stage, food services kitchen, serving areas, and support spaces—an investment in our community using taxpayer bond dollars.


Upon completion, the existing portable cafeteria will be removed. The project also includes roll-up doors for exterior access, surrounding landscaping, and infrastructure for a new garden.


Architect: Hamilton + Aitken Architects
Anticipated Completion: Winter/Spring 2025
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.

Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map

Formwork for Concrete Paving

User uploaded image
zoom_out_map

Your Project Team

User uploaded image
zoom_out_map

New Concrete Pathway

Shannon Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter