SHANNON ES - MPR Project
November 2025

Project Updates - November 2025
Activities This Month
- Installation of all electrical, mechanical and plumbing fixtures is complete.
- The new floors were completed, including epoxy flooring, polishing the concrete and wood flooring on stage.
- New wall paneling has been installed in the dining area.
Activities Next Month
Finish installing the kitchen equipment
Final coat of interior paint
Install window coverings
Install new concrete sidewalks
New asphalt paving for the fire road and service entrance
Project Overview
Project Scope: This project will construct a new multi-purpose building featuring a dining area, stage, food services kitchen, serving areas, and support spaces—an investment in our community using taxpayer bond dollars.
Upon completion, the existing portable cafeteria will be removed. The project also includes roll-up doors for exterior access, surrounding landscaping, and infrastructure for a new garden.
Anticipated Completion: Winter/Spring 2025