Lake ES -School Replacement Project
March 2025

Project Updates - March 2025
Construction Activity
Building E and F (Kindergarten Wings)
- The installation of the mechanical, electrical, plumbing, and fire sprinkler systems behind the wall and above the ceiling will be complete this month
- Scaffolding has been placed, and the water barrier system and lath will continue to be installed over the coming weeks to prepare the building for exterior stucco
Building D (Cafeteria)
- Rough framing and installation of the acoustical metal deck is in progress
- Drilling the piers for the canopy foundations has begun
- The installation of the mechanical, electrical, plumbing, and fire sprinkler systems behind the wall and above the ceiling will continue
Project Overview
- Project Scope: The primary purpose of this project is to replace the school campus. The campus will be occupied during the duration of this project. The project has two main construction phases. The project design started in August 2021, and the first phase of construction is complete. Phase 2 is scheduled through Fall 2025. The first phase included new buildings and site work on the East half of the campus, and the second phase will include new buildings and remaining site work on the West half of the campus. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Quattrocchi Kwok Architects - QKA
- Anticipated Completion: Fall 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net