June 30, 2025 Bond Update

June 30, 2025 Bond Update
June 30, 2025Bond Update

SUMMER BREAK? NO BREAK HERE!😎🚧 SUMMER BREAK? NO BREAK HERE!😎🚧

On Schedule for our First Home Football Game 🏈

Work continues across the district during summer break, with several major projects progressing on schedule. At the stadium, construction remains on track, with artificial turf installation scheduled to begin shortly after the Fourth of July. Phase one of the softball and baseball complex improvements is set to begin this month. Planning for traffic flow and parking lot updates is nearing completion, with multiple site meetings taking place to finalize key details.


Fire alarm system upgrades are actively underway and progressing on schedule. Carpet installation at both the middle school and high school is in progress as well. In addition, site preparation will soon begin for the district’s new, state-of-the-art transportation and maintenance facility.


These efforts, along with numerous other facility improvements, are setting the stage for a strong start to the upcoming school year!

MEET OUR TEAM! 🌟 MEET OUR TEAM! 🌟

zoom_out_map

TowerPinkster🤝

Partner Spotlight: TowerPinkster Architechs


TowerPinkster is a Michigan-based architecture and engineering firm with a long-standing reputation for designing innovative, functional, and community-focused educational spaces. With offices in Grand Rapids, Kalamazoo, and Grand Haven, the firm brings deep experience in K-12 design, including facility planning, bond support, and modern learning environments.


TowerPinkster combines architecture, engineering, interior design, and technology services under one roof to create cohesive, future-ready solutions. Their collaborative process actively engages school leadership, staff, students, and the community to ensure each project reflects the district’s vision and values. Known for their sustainable practices and attention to educational trends, TowerPinkster has helped dozens of Michigan districts maximize the impact of their bond investments.


For our bond project, TowerPinkster is serving as our architectural and design partner, guiding us through planning, community engagement, and the development of spaces that support 21st-century learning while honoring our district’s unique identity.

NEW UPDATES NEW UPDATES

Bid Packages Approved at June 23 Board Meeting📅 Bid Packages Approved at June 23 Board Meeting📅

Bid Package 1A Athletic Equipment Related to Stadium

Scope: Athletic Equipment (FF&E)

  • Equipment for all athletics utilizing new turf field and track & field complex
  • Track & Field, Football, Soccer, Lacrosse


Budget: $376,637.00

  • Previously approved: $180.580.00
    • $173,705.00 (new bleachers)
    • $6,875.00 (bleacher alternates)
  • Needing approval: $196,057.00
    • (athletic equipment)

Bid Package 1C Baseball & Safteball Upgrades Phase 1 of 2

Scope: New Fence, Irrigation, and Enhancements to Infields

  • Budget: $741,384.75
  • Greatest Maximum Price (GMP): $750,347.00
    • Construction Contingency: $13,957.00
    • Owner Contingency: $13,957.00
  • Timeline: Summer / Fall 2025
  • Bidder Participation
    • 7 bidders total

Bid Package 2 Maintenance & Transportation

Scope: PEMB & Tree Clearing

  • Budget: $1,368,612
  • GMP: $1,444,060
    • Construction Contingency: $26,860 (2%)
    • Owner Contingency: $26,860 (2%)
  • Timeline: October 2025 - October 2026
  • Bidder Participation
    • 7 bidders total

Bid Package 1B - Traffic Flow Relief on the Way! 🚌🚦🚸 Bid Package 1B - Traffic Flow Relief on the Way! 🚌🚦🚸

Campus Traffic Flow: HS/MS Bus Loop and Parent Pick-up/Drop-off

Considerable planning has been accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:


  • Fully separate buses from carpool and staff traffic at both the middle and high schools
  • Reconfigure the carpool traffic routes at both the middle and high schools
  • Add needed parking in front of middle and high schools
  • Add a 'thru' drive east to west for bus traffic to move within our district
  • Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow



Above: concept design of bus loading lanes on the south side of the middle and high schools.

Below: concept design of parking and carpool lanes on the north side of middle and high schools.

Kickoff for Design for Middle and High School Renovations🔬🏋🏻🧑🏻‍🍳

In May and June the design team will be meeting with key staff to gather input on a variety of upcoming projects, including:


  • renovations of old middle and high school science rooms
  • renovation/expansion of existing high school weight room
  • renovation of existing high school girls and boys locker rooms

ON-GOING PROJECTS 📆 ON-GOING PROJECTS 📆

Bid Package 1C: SOFTBALL AND BASEBALL FIELDS Bid Package 1C: SOFTBALL AND BASEBALL FIELDS

Batter Up! ⚾🧢🥎

The upcoming improvement project for the baseball and softball fields will focus on enhancing safety, accessibility, and overall field quality. The project includes the installation of new fencing and backstops for both fields to match the updated fencing planned for the football stadium. Emergency vehicle access points will also be added to both fields.


Upgrades will include new irrigation systems and a modernized controller for better zone management. Since the bladder tanks were replaced two years ago, they will remain in place. On the baseball field, the infield will be re-sodded and the area between third base and home plate will be leveled. Both outfields are currently in good condition and do not require regrading or reseeding.


Additional improvements include the installation of new foul line markers on both fields and cement pads in front of each dugout, extending from the dugout entrances to the safety fences.

BID PACKAGE 1A - STADIUM WORK BID PACKAGE 1A - STADIUM WORK

Week 16

Work continues to progress across the site as part of Bulletin 2. Fine grading and top stone placement are underway, preparing the area for final surfacing. The northeast corner of the site remains untouched in anticipation of the scoreboard delivery and installation. Concrete has been successfully poured at the concessions area, and installation of fence posts has begun around the stadium interior along the exterior of the track. At the south detention pond, fence fabric installation is complete with the exception of the gate. Foundational preparation for the scoreboard structure has been completed, and trench drains have been installed around the stadium perimeter to support proper drainage.



Site work continues to advance with fine grading of stone ongoing on the football field. Concrete placement is progressing in the field event areas, while installation of the scoreboard foundation is scheduled to move forward. Fence installation continues around the interior of the stadium. Bulletin 3 has been released, initiating stormwater-related work. Bulletin 2 work remains in progress, though slightly delayed due to recent weather conditions. This includes final grading of the road and parking lot areas, along with final preparation work in advance of asphalt paving.

Time to Score the Scoreboard! 🥇

Part of BP1 includes an allocation for a new score board. Above is a concept design roughly 20' x 28' - a substantial upgrade from our current board, which will be repurposed to the new multi-purpose field south of the stadium. The scoreboard will be moved to the North endzone, to make way for upcoming renovations to the southern entrance in a later bid package.

BP1A Contingency Update BP1A Contingency Update

HIGH SCHOOL FIRE ALARM UPDATE Bid Package 1D⚡🔥 HIGH SCHOOL FIRE ALARM UPDATE Bid Package 1D⚡🔥

Recent progress on BP1D includes the pulling of new wire and conduit in both the mezzanine and penthouse areas to support new duct detectors. New boxes have been installed on the ductwork to accommodate these devices. In the courtyard, new horn and strobe devices have been installed, along with sleeves for the remaining new devices. A ground fault issue in the gymnasium area was identified and repaired, and all associated work in the gym has now been completed.

Stadium Construction Phases Stadium Construction Phases

zoom_out_map

Stadium Work, Phase 2 Summer 2026

It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026 and will include renovations to the current press box and the addition of a new sound system.

Stadium Work, Phase 3

Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvements to the current entryway on the North side of the stadium.

BID PACKAGE 2A PLANNING UNDERWAY BID PACKAGE 2A PLANNING UNDERWAY

zoom_out_map

Bold Designs for New Maintenance and Transportation Complex

Exciting progress is underway as we move forward with the design of a new Transportation and Maintenance Building, which is set to begin construction this fall! Located just west of the current high school, this much-needed facility will replace outdated and undersized buildings that no longer meet modern safety standards.


Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker and shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.


This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.

ARCHIVED INFORMATION ARCHIVED INFORMATION

Construction Bid Packages Explained Construction Bid Packages Explained

zoom_out_map

Construction Bid Packages Exlplained

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


Please note: The bid packages listed below are currently in various stages of design. Additional bid packages, including those for field turf, the middle school cafeteria, technology, the natatorium, and others, have not yet entered the design phase but will be developed and updated in the future.


Bid Package 1A - Stadium Inner Scope

  • Replace field with turf
  • Replace track & field
  • Replace inner perimeter fencing
  • Fall 2024 - project design
  • Winter 2024 - project bidding
  • Spring 2025 - project construction


Bid Package 1B - Campus Traffic Flow & Parking

  • High School and Middle School parent carpool loop reworked
  • Separation of buses from carpool/community traffic
  • Expanded parking in front of the middle and high school
  • Stadium press box renovations
  • Spring 2026 - project bidding
  • Summer of 2026 - project construction


Bid Package 1C - Baseball & Softball Field Upgrades

  • Update irrigation system
  • Updated perimeter fencing
  • Spring 2025 - project bidding
  • Summer 2025 - construction


Bid Package 1D - Middle/High School Fire Alarm System Replacement

  • Winter 2025 - project bidding
  • Summer 2025 - construction


Bid Package 2A - New Construction Transportation & Maintenance Facility

  • Winter 2025 - Design Development
  • Summer 2025 - project bidding
  • Fall 2025 - Fall of 2026 - construction

Our Plan. Our Students. Our Future. Our Plan. Our Students. Our Future.

zoom_out_map

Our focus revolves around five key objectives for the bond:


  1. Preserve existing assets
  2. Prioritize safety and security
  3. Provide future-focused academic and extracurricular experiences for our students
  4. Enhance infrastructure
  5. Demonstrate fiscal responsibility


Safety & Security:

  • Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
  • Replacement of outdated, unreliable security equipment at each building

Transportation:

  • Continued replacement of an aging bus fleet

Academic Learning Spaces + Experience:

  • Replacement of original, aged classroom equipment and furniture at middle and high schools
  • Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.

Fine Arts:

  • Upgrades to lighting and media equipment at the high school auditorium

Infrastructure:

  • Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
  • Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
  • Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
  • Addition of cooling to main gymnasiums at the high school

Student Athletic Experience:

  • Renovation of aged high school locker rooms
  • Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
  • New high school track - the current track is backwards and nearly unusable in the current condition
  • Upgrades to baseball and softball fields
  • Construction of a new multi-use turf field (soccer, lacrosse, football)
  • Maintenance of existing practice fields; addition of a new outdoor practice space

Other Construction:

  • Addressing overcrowding in the current Middle School cafeteria
  • Replacement of aged, quickly deteriorating tennis courts
  • Replacement of aged transportation building and maintenance building
  • Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
  • Construction of a student/community pool

Upcoming Upcoming

Additional Information at your Fingertips Additional Information at your Fingertips

zoom_out_map

Supporting Docments

Click on the buttons below to review salient information

Bond 2024 Website
General Bond 2024 Information
zoom_out_map

Construction

zoom_out_map

Architech

zoom_out_map

Owner's Representative

Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter