Hercules CNP

August 2024

Hercules CNP August 2024
HerculesCNPAugust 2024

Project Updates - August 2024 Project Updates - August 2024

zoom_out_map

Construction Completed Last Month

  • Roofing completed
  • Ongoing installation of cloud ceilings in high school classrooms
  • Application of the plaster finish coat
  • Ongoing installation of the tile in restrooms
  • Ongoing demolition of classroom portables
  • Connecting the fire water and sewer lines
zoom_out_map

Construction Work Planned for This Month

  • Exterior Paint
  • Removal of the scaffolding after the stucco is applied
  • Completion of T-bar ceiling grids
  • Installation of restroom partitions
  • Installation of electrical trims/finishes
  • Field measurement for the casework
  • Asphalt paving
  • Installation of artificial turf at seat walls

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
  • Architect: DSK Architects
  • Contractor: Soltek Pacific Construction
  • Anticipated Completion: Fall / Winter 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Portables Demolition

zoom_out_map
zoom_out_map

Tile Installation

Hercules Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter