Stege Rebuild Project
May 2026

May 2026 - Project Update
Activities This Month
- Thank you to everyone who joined us for the Quarterly Update Meeting!
- Soil testing and removal below and around the removed underground storage tanks.
- Comments on the Phase 2 design were received from the Division of State Architect (DSA). The design team is working on responding to these comments and resubmitting to the State.
Activities Next Month
- Complete mass grading of the site and soil haul-off.
- Continue preparing the site and building foundations for future construction.
- Install underground electrical pathways.
- Install domestic, fire, and irrigation backflow preventers.
- Continue installation of underground stormwater systems.
- Connect underground stormwater and sewer to city services.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Project Summary
The Stege campus rebuild, now in the design phase, will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.