KHS Modernization Project

March 2026

KHS Modernization Project March 2026
KHS ModernizationProjectMarch 2026

March 2026 - Phase 1 Demolition March 2026 - Phase 1 Demolition

User uploaded image
zoom_out_map

Activities This Month

  • In the areas between the new classroom building and the existing 300/400 building, we have installed the sewer system and are currently installing all water lines, power, and fiber conduits.

  • The East Bay Municipal Utility District water tie-in for new Building A is scheduled.
  • We are working on prepping and furnishing the Building B pad for lime treatment and certification.

  • Preparation for the new main electrical service has begun.

User uploaded image
zoom_out_map

Activities Next Month

  • Inspections for the new main electrical service.
  • Building pad preparation planned for spring break.

Project Overview Project Overview

User uploaded image
zoom_out_map Show in original size
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net