KHS Modernization Project
March 2026

March 2026 - Phase 1 Demolition
Activities This Month
In the areas between the new classroom building and the existing 300/400 building, we have installed the sewer system and are currently installing all water lines, power, and fiber conduits.
- The East Bay Municipal Utility District water tie-in for new Building A is scheduled.
We are working on prepping and furnishing the Building B pad for lime treatment and certification.
Preparation for the new main electrical service has begun.
Activities Next Month
- Inspections for the new main electrical service.
- Building pad preparation planned for spring break.