Referendum Project Update
May 2023
Due to the upcoming projects and construction, New Providence High School and Middle School buildings and grounds will be closed to the public this summer. More detailed information regarding NPHS Athletics and co-curricular activities will be forthcoming from Mr. Henry, NPHS Principal.
Allen W. Roberts School and Salt Brook School will host the District summer programs, such as ESSER and ESY.
Classroom Furniture
We are very excited to receive all of our new mobile and flexible furniture in the summer of 2023! Each school has had a full room of new furniture throughout the spring to explore its versatility, and create different learning environments to empower our students.
Capital Improvement Projects
High School Track Replacement
Scheduled to be installed in Summer of 2023. Please take a look at the new color scheme for the high school track!
High School Partial Roof Replacement
Scheduled to be completed in Summer of 2023.
High School / Middle School Partial Floor Replacement
Scheduled to be completed in Summer of 2023. Logos will be embedded into the floor in different areas.
High School / Middle School Staff Restroom Upgrades
Scheduled to be completed in Summer of 2023.
High School Bleacher Replacement
Scheduled to be completed in Summer of 2023.
*In addition, as part of the operating budget, the HS gym floor will also be refinished concurrently with the bleacher replacement.
The room divider will also be replaced in the HS gym. The Fold-Up Gym Divider Curtains electronically divide one space into two with the turn of a key. Enclosed is an example, but the color will be Pioneer Green!
Heating, Ventilation and Air Conditioning Project
Due to at least a 10 month lead time to secure parts and product, the HVAC project will commence in Summer 2024. Each school will have its own contractor, so work will proceed concurrently.