Time to Bloom Update 10/12/25
A monthly update on the RTMSD K-1 Early Learning Center
Board of School Directors Work Session Presentation - Staff Input
At the October 9 Work Session, the School Board continued discussions on the K-1 Early Learning Center and other topics. A recording of the full presentation is available on our YouTube channel. The slide show presentation is available on the RTMSD website.
Highlights
- Architectural renderings of the new K-1 Early Learning Center.
- An update on the land development process, including a traffic study, stormwater management, sewer and wastewater management, and environmental and zoning compliance.
- An update on the construction timeline, with estimated completion of the K-1 Early Learning Center in August 2028.
A recording of the full presentation is available on our YouTube channel, and the slideshow presentation is available on the district’s website.
Staff input
The Board also considered a summary of meetings with user groups in a variety of areas (including staff members in special education, IT, safety and security, food service, transportation, administration and counseling), who shared input on the design of the K-1 Early Learning Center. In the words of Ianni Vardouniotis, ICS Senior Project Manager, "We want, when faculty and staff show up to the building for the ribbon cutting, for all of their needs to have been met."
What’s next
As we look ahead, here’s what’s next for the School Board:
- Continue land development, including a traffic study and a preliminary land development drawing.
- Continue design development, including user group meetings and a geotechnical investigation.
We remain committed to keeping you informed as these projects move forward. Thank you for your continued partnership as we plan for facilities that meet the needs of today’s students and generations to come.
Proposed Timeline
Proposed Project Milestones 2025-2028
March 2025-June 2025: Schematic Design
June 2025-October 2025: Design Development, with Approval of Act 34 Resolution in November 2025 and Act 34 Hearing in January 2026
November 2025-May 2026: Construction Documents
June 2025-August 2026: Bidding, with Board Approval of Bids in August 2026
September 2026-August 2028: Construction
August 2028: Move-in