KHS Modernization Project
May 2026

May 2026 - Phase 1 Utility and Site Preparation
Activities This Month
- Site utility work along the 300, 400, and 800 Buildings continues with the installation of electrical, fiber, and power conduits.
- Firewater connection from Cutting Blvd completed, including repaving the street trench.
- Spring break activities included the lime treatment of the new building pads and installing a new joint trench between the stadium and the 800 Building.
- Pad maintenance activities for Buildings A and B will continue throughout the month.
Activities Next Month
- New power service connections coordinated with PG&E for late May. Temporary power will be utilized during the switch over process to maintain site operations.
Project Overview
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net