DCSC Construction Update

Update #18

DCSC ConstructionUpdateUpdate #18

August 2025 August 2025

Welcome back to another school year and another round of exciting construction updates! We have some exciting news to share as we enter our first semester...


Keep reading for more detailed updates and photos of our progress!

South Progress South Progress

South is Complete!

We are so excited to announce that construction at South Elementary is officially complete! Over the summer, our crews worked hard to make sure everything was ready for the new school year. We can’t wait to make the most of our many new and renovated spaces with our students. We have officially completed...


  • A renovated library
  • A renovated/expanded gym
  • A renovated cafeteria
  • Renovated classrooms
  • A new classroom wing
  • A new behavior support room
  • A new art room
  • A new front office/main entrance
  • Additional outdoor walkways
  • A renovated music room
  • AND MORE!


Below are just a few photos to show the huge progress made! You will also find a photo from our Ribbon Cutting Ceremony, which took place on Monday, August 4.

User uploaded image
zoom_out_map

Classroom

User uploaded image
zoom_out_map

Art Room

User uploaded image
zoom_out_map

Gym

User uploaded image
zoom_out_map

Front Office

User uploaded image
zoom_out_map

Media Center

User uploaded image
zoom_out_map

Outdoor Walkway

Ribbon Cutting Ceremony
zoom_out_map Show in original size

Ribbon Cutting Ceremony

Thank you to all of our special guests!

High School Progress High School Progress

The high school has work happening all over the building, and it feels like new progress is made every single day! In fact, we are happy to share that a few big projects were completed over the summer! The new main entrance, front office, guidance suites, classroom wing, student services office, and football stadium are officially completed and ready for action! The band room, choir room, classroom renovations, weight room, new pool, athletic building, AND MORE are all well underway. We hope to bring more exciting updates of completion very soon.
User uploaded image
zoom_out_map

Main Entrance

User uploaded image
zoom_out_map

Front Office

User uploaded image
zoom_out_map

Classrooms

User uploaded image
zoom_out_map

Athletic Building

User uploaded image
zoom_out_map

Pool

User uploaded image
zoom_out_map

Stadium

User uploaded image
zoom_out_map

Media Center

User uploaded image
zoom_out_map

Choir Room

User uploaded image
zoom_out_map

PLTW Classroom

Recent Videos Recent Videos

DCSC Master Campus Plan Summer Update 2025

Join Dr. Shafer for an exciting update on the progress at South Elementary and Danville Community High School as part of our DCSC Master Campus Plan!
DCSC Master Campus Plan Summer Update 2025
User uploaded image
zoom_out_map

Follow us to learn more!

This blog post, as well as other information (videos, photos, etc.), can all be found on our website and social media. Be sure to follow us to see what is happening now and what is happening next!

Email: aengland@danville.k12.in.us
Website: https://www.danville.k12.in.us/
Phone: 317-745-2212
Facebook: https://www.facebook.com/DCSCWarriors
Twitter: @DCSCWarriors

DCSC Warriors
DCSC is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter