Activities This Month

Buildling A

  • Finished excavation and prepped the ground for building foundations.
  • Installed underground plumbing and electrical lines beneath the footings.
  • Placed steel reinforcement and poured concrete footings in two areas.
  • Started work on the elevator pits.

Building B

  • Completed underground plumbing and site prep.
  • Installed foundation reinforcement and anchor bolts.
  • Completed inspections and poured footings.
  • Footings reached full strength; forms removed and site cleaned.
  • Continued elevator pit work, including waterproofing.
User uploaded image
zoom_out_map

Activities Next Month

Buildling A

  • Inspections of reinforcement steel and anchor bolts.
  • Continue foundation work in the remaining area.
  • Finish footing pours and begin floor slab preparation.
  • Continue elevator pit construction, including waterproofing.
  • Ongoing coordination on underground utility work.

Building B

  • Complete remaining footing work near Building B.
  • Finish elevator pit walls, waterproofing, and backfill.
  • Complete pier inspections.
  • Coordinate utility room piping installation.
  • Begin preparations for structural steel work, starting in early October.

Project Overview Project Overview

Phase 1 scope includes Building A - Office & Classrooms and Building B - Cafeteria and Performance Space
zoom_out_map Show in original size

Phase 1.3 Scope

This current phase of work includes two new buildings, the staff/visitors parking lot, and a remodel of the K Quad. Building A is a two-story classroom building along Cutting Blvd with the administrative, student services, and health center offices in the eastern wing. Building B is a combination performing arts and cafeteria supported by a full-cook kitchen, stage, and back of house areas.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.



Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
KHS Modernization Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by