KHS Modernization Project
September 2026

September 2026 - Project Updates
Activities This Month
Buildling A
- Finished excavation and prepped the ground for building foundations.
- Installed underground plumbing and electrical lines beneath the footings.
- Placed steel reinforcement and poured concrete footings in two areas.
- Started work on the elevator pits.
Building B
- Completed underground plumbing and site prep.
- Installed foundation reinforcement and anchor bolts.
- Completed inspections and poured footings.
- Footings reached full strength; forms removed and site cleaned.
- Continued elevator pit work, including waterproofing.
Activities Next Month
Buildling A
- Inspections of reinforcement steel and anchor bolts.
- Continue foundation work in the remaining area.
- Finish footing pours and begin floor slab preparation.
- Continue elevator pit construction, including waterproofing.
- Ongoing coordination on underground utility work.
Building B
- Complete remaining footing work near Building B.
- Finish elevator pit walls, waterproofing, and backfill.
- Complete pier inspections.
- Coordinate utility room piping installation.
- Begin preparations for structural steel work, starting in early October.
Project Overview
Phase 1.3 Scope
This current phase of work includes two new buildings, the staff/visitors parking lot, and a remodel of the K Quad. Building A is a two-story classroom building along Cutting Blvd with the administrative, student services, and health center offices in the eastern wing. Building B is a combination performing arts and cafeteria supported by a full-cook kitchen, stage, and back of house areas.
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net