Activities This Month
The former south side parking lot solar panels have been successfully demolished.
We have also excavated the sewer line to accommodate new site infrastructure improvements.
We are currently working on installing a new fire-water line across the site that ties into the existing fire water loop.
On the northwest side of the site, we continue and advance installation of the storm drain system.
Activities Next Month
Installing the new domestic water line along the west side of the site
Certify the new classroom building pad
Complete the storm drain system
Project Overview
The Richmond High School Modernization project involves demolishing a portion of the classroom building to make way for a new two-story building along 23rd Street. The remaining classroom section will be updated, including the installation of new windows. The large gym and the 600 Buildings will receive a refresh.
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23