Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
Renaissance @ Rand
Project Status: December 19, 2025
Project Completion: 59% complete
Current Status: Completed demo and rigging of 2nd boiler
Upcoming Milestones: Installing initial piping
Contract to Date: $3,785,100.00
Paid to Date: $2,016,285
George Inness
Project Status: December 19, 2025
Project Completion: 63% complete
Current Status: Completed burner install on 2nd boiler
Upcoming Milestones: Complete gas train, waterlines, and electrical connections
Bradford Elementary
Project Status: December 19, 2025
Project Completion: 59% complete
Current Status: Completed demo and rigging of 2nd boiler
Upcoming Milestones: Installing initial piping
Watchung Elementary
Project Status: December 19, 2025
Project Completion: 60% complete
Current Status: Demo, rigging, initial piping complete to 2nd boiler
Upcoming Milestones: Install burner; electrician to begin making connections to 2nd boiler
Edgemont Elementary
Project Status: December 19, 2025
Project Completion: 60% complete
Current Status: Completed demo and rigging of 2nd boiler
Upcoming Milestones: Installing initial piping
Northeast Elementary
Project Status: December 19, 2025
Project Completion: 60% complete
Current Status: Installing piping to the 2nd boiler
Upcoming Milestones: Install burners, gas train, and water lines