EPCUSDConstruction UpdateJune 2023

Summer Construction is in full swing and on target

The final phase of referendum project at John Mills and Elmwood has begun. This summer's construction will complete renovations and additions at both elementary schools. We are very excited to be able to welcome back students this fall to newly renovated learning spaces. At Elmwood the entire second floor is being renovated and at John Mills, the remaining north end of the building is being completed. Please follow the progress of our construction by going to the Construction tab on our district website https://www.epcusd401.org/

This summer the high school is also undergoing an extensive construction project. The old library space in being renovated into a modern media center with additional classrooms and learning spaces for students. In addition, the LGI is being renovated into a classroom and much needed office spaces, which will provide our support services their own space to work with students. The high school renovations are scheduled for completion this August.

Elmwood Elementary

Demolition of the second floor at Elmwood is complete. The construction crews have begun framing out the new classrooms and breakout rooms. Once the walls and wiring is complete, drywall and flooring will be installed. Elmwood is on pace for students to return the end of August.

https://epcusd401.smugmug.com/Construction/Elmwood-Construction-Project

zoom_out_map

First day of demolition

zoom_out_map

Demolition of old classrooms

zoom_out_map

Framing the new classrooms

John Mills Elementary

The new preschool playground is complete and ready for student use when school resumes this fall. Demolition of the remaining renovation areas on the north side of John Mills is complete and the framing for the new technology, music and art classrooms have begun.

https://epcusd401.smugmug.com/Construction/John-Mills-Construction-Project

zoom_out_map

Removing concrete parking along alleyway

zoom_out_map

Demolition of old classrooms on first floor

zoom_out_map

Demolition of second floor classrooms

High School

The high school renovations of the library and Large Group Instruction (LGI) is ahead of schedule and due to an early start on demolition the construction company anticipated both of these newly renovated spaces to be available for use when school resumes this fall.

https://epcusd401.smugmug.com/Construction/EPHS-Construction-Project

zoom_out_map

New classroom windows being installed

zoom_out_map

Framing walls in new media center

zoom_out_map

Removing the sloped floor in the LGI

Link to Construction Website
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter