SHANNON ES - MPR Project

July 2024

SHANNON ES - MPR Project July 2024
SHANNON ES- MPR ProjectJuly 2024

Project Updates - July 2024 Project Updates - July 2024

zoom_out_map

Construction Completed Last Month

  • Demolition of existing asphalt
  • Clear and grub vegetation
zoom_out_map

Construction Work Planned for This Month

  • Building Foundations
  • Underground Utilities

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to build a new multi purpose room with dining area, stage, and food services kitchen, servery, and support spaces. After the completion of the new building, the existing cafeteria portable will be removed. The project will include roll-up doors to support connection to the exterior, landscaping around the building, and infrastructure for a new garden. This project is an investment in our community through the use of taxpayer bond dollars.
  • Architect: Hamilton + Aitken Architects
  • Anticipated Completion: Fall/Winter 2025
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Existing Cafeteria

To be removed after the completion of the new building

zoom_out_map

Your Project Team

zoom_out_map

Site Plan

New Multi Purpose building will be constructed south of the existing classroom buildings behind the existing cafeteria.

Shannon Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter