Stege Rebuild Project
November 2026

November 2026 - Project Updates
Activities This Month
- Continue under-slab plumbing and electrical
- Continue Vapor Intrusion Mitigation System
- Community Meeting
- Tuesday December 1st - 7:00 pm to 8:00pm
- At Booker T Anderson Jr. Community Center - 960 S. 47th Street, Richmond
- Join us for a presentation on the construction schedule and current construction activities
Activities Next Month
- Complete installation of foundation rebar
- Pour concrete building foundations
- Installation of under-slab plumbing and electrical
- Building slab formwork
- Set steel columns at lunch canopy
- Begin installation of Vapor Intrusion Mitigation System
Project Summary
The Stege campus rebuild will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23