OPERATIONS SPOTLIGHT
Volume 1
2025 BOND PROGRAM UPDATE
The 2025 Bond Program, supported by our community last November, continues to make significant progress across multiple district facilities. From new playgrounds and building improvements to critical system upgrades, exciting work is happening throughout the district.
BERTHOUD ELEMENTARY SCHOOL
Early Childhood Playground Complete!
Grand Opening Celebration was held on September 23rd
The new Early Childhood playground is complete! Design details for the larger project will be finalized this month. Site fencing and a job trailer will arrive later this year, paving the way for interior construction to begin over the holiday break.
IVY ELEMENTARY SCHOOL
Site Preparation Underway
Initial site preparation for the administration and gym addition is underway at Ivy Elementary. Construction fencing and the job trailer have been placed.
MARY BLAIR FACILITY
Parking Lot Complete
Parking lot construction is complete, and long-term repurposing plans are underway.
PONDEROSA ELEMENTARY SCHOOL
Playground Improvements Complete
Ponderosa Elementary School has completed its playground improvements, featuring new equipment and fall surface.
IMPROVEMENTS ACROSS THE DISTRICT
Investing in Safe, Modern Learning Environments
✓ Critical mechanical system upgrades are actively being executed at several locations.
✓ Stage lighting and adjacent equipment projects are complete at 5 auditoriums.
✓ Recent adjustments to the 5-year master schedule resulted in accelerated project timelines, allowing a dozen initiatives to move forward for earlier completion.
COMMUNITY OVERSIGHT
Transparency. Accountability. Progress.
The Citizens’ Bond Oversight Committee (CBOC) has convened twice to review the program. The committee has also made key decisions regarding the initial use of the bond premium while ensuring ongoing transparency and accountability for our community.