Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
District Wide Boiler Replacement
Replacement of aged boilers, feeder tanks, and electrical components as required
Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00
Renaissance @ Rand
Project Status: March 20, 2026
Project Completion: 88% complete
Current Status: Both boilers are installed; insulation is being completed; draft controls are being installed
Upcoming Milestones: Feed unit piping to be completed; painting to be completed; boiler #2 start up
George Inness
Project Status: March 20, 2026
Project Completion: 89% complete
Current Status: Completing insulation on boiler #2; draft controls installed; feed unit piping completed; painting completed
Upcoming Milestones: Boiler #2 Start up
Bradford Elementary
Project Status: March 20, 2026
Project Completion: 88% complete
Current Status: Both boilers are complete; insulation is being completed; draft controls installed; feed unit piping is being completed.
Upcoming Milestones: Boiler #2 start up; painting to be completed.
Watchung Elementary
Project Status: March 20, 2026
Project Completion: 90% complete
Current Status: Both boilers complete; insulation complete; draft controls installed; painting complete
Upcoming Milestones: Boiler #2 start up
Edgemont Elementary
Project Status: March 20, 2026
Project Completion: 87% complete
Current Status: Both boilers are complete; insulation is being completed; draft controls installed; feed unit piping is being completed
Upcoming Milestones: Boiler #2 start up; complete painting
Northeast Elementary
Project Status: March 20, 2026
Project Completion: 86% complete
Current Status: Insulation is being completed; draft controls installed
Upcoming Milestones: Feed unit piping to be completed; painting to be completed; boiler #2 start up
