Montclair Public Schools

September 16, 2024

Montclair Public Schools  September 16, 2024
MontclairPublic Schools September 16, 2024

Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

District Wide Boiler Replacement

Replacement of aged boilers, feeder tanks, and electrical components as required

Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00

Renaissance @ Rand Renaissance @ Rand

Project Status: March 20, 2026

Project Completion: 88% complete

Current Status: Both boilers are installed; insulation is being completed; draft controls are being installed

Upcoming Milestones: Feed unit piping to be completed; painting to be completed; boiler #2 start up

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: March 20, 2026

Project Completion: 89% complete

Current Status: Completing insulation on boiler #2; draft controls installed; feed unit piping completed; painting completed

Upcoming Milestones: Boiler #2 Start up

User uploaded image
zoom_out_map Show in original size

Bradford Elementary Bradford Elementary

Project Status: March 20, 2026

Project Completion: 88% complete

Current Status: Both boilers are complete; insulation is being completed; draft controls installed; feed unit piping is being completed.

Upcoming Milestones: Boiler #2 start up; painting to be completed.

User uploaded image
zoom_out_map Show in original size

Watchung Elementary Watchung Elementary

Project Status: March 20, 2026

Project Completion: 90% complete

Current Status: Both boilers complete; insulation complete; draft controls installed; painting complete

Upcoming Milestones: Boiler #2 start up

User uploaded image
zoom_out_map Show in original size

Edgemont Elementary Edgemont Elementary

Project Status: March 20, 2026

Project Completion: 87% complete

Current Status: Both boilers are complete; insulation is being completed; draft controls installed; feed unit piping is being completed

Upcoming Milestones: Boiler #2 start up; complete painting

User uploaded image
zoom_out_map Show in original size

Northeast Elementary Northeast Elementary

Project Status: March 20, 2026

Project Completion: 86% complete

Current Status: Insulation is being completed; draft controls installed

Upcoming Milestones: Feed unit piping to be completed; painting to be completed; boiler #2 start up

User uploaded image
zoom_out_map Show in original size

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter