At the September 2026 Board meeting, MISD Executive Director of Facilities gave an update on the November 2025 Bond projects.
Elementary #10
- Design Development has been completed by VLK Architects and approved by Magnolia ISD
- 50% Construction Documents are due September 15, 2026
- B&C Constructors is set to provide an early estimate of the total price
- 100% Construction Documents are scheduled for December 2026
- The Guaranteed Maximum Price (GMP) is scheduled for approval by the Board on February 8, 2027
- Construction begins - March 2027
High School #3
- Schematic design by VLK Architects is in-progress for the floor plan and site plan
- A Design Development presentation for the Board is scheduled for December 2026
- 50% Construction Documents are expected by January 2027
- Tentatively scheduled for bidding in April/May 2027
- the GMP is tentatively scheduled for presentation to the Board for approval at the June or July 2027 Board meeting
Elementary #11
- Geotechnical exploration and topographic survey are in-progress
- Design of the architectural site plan by VLK Architects is in progress
- Civil site plan should start in October/November 2026
- Building floor plan should be very close to the Elementary #10 plan
- Exterior design should start early 2027
Existing High School Additions
- Projects are in the Design Development stage by PBK Architects
- Constructions Documents are scheduled for early 2027
- Bidding is scheduled for spring 2027
Magnolia ISD
November 2025 Bond
Email: info@magnoliaisd.org
Website: www.magnoliaisd.org
Location: 31141 Nichols Sawmill Road, Magnolia, TX, USA
Phone: 281-356-3571
Facebook: https://www.facebook.com/MagnoliaISD
Magnolia ISD
Magnolia is using Smore to create beautiful newsletters