Hercules CNP

August 2023

Hercules CNP August 2023
HerculesCNPAugust 2023

Project Updates - February 2024 Project Updates - February 2024

zoom_out_map

Construction Completed Last Month

  • Started Framing on the High School side
  • Completed wall framing on the Middle School side
  • Installed glulam beams and started roof framing on the Middle School Side
  • Started electrical rough-in
  • Ongoing placement of structural steel
zoom_out_map

Construction Work Planned for This Month

  • Continue framing on the High School side
  • Install glulam beams and start roof framing on the High School Side
  • Roof framing will be completed on the Middle School side and start on the High School side
  • Ongoing electrical and plumbing rough-in

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
  • Architect: DSK Architects
  • Contractor: Soltek Pacific Construction
  • Anticipated Completion: Summer 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Rough-In

Electrical boxes and conduit
zoom_out_map
zoom_out_map

Workroom

Roof joists and ceiling hangers
Hercules Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter