May 2, 2025 Bond Update
MEET OUR TEAM! 🌟
Veridus Group🤝
In this update, let's get to know one of our teams a bit better.
The Veridus Group, Inc., headquartered in Indianapolis, Indiana, is a multidisciplinary firm specializing in Owner’s Representation, civil engineering, and economic development services across the Midwest, including Michigan. Their Owner’s Representation services are primarily delivered through Veridus Advisors, a subsidiary focused on guiding clients through complex capital projects from inception to completion.
What Veridus Owner’s Representatives Do
Veridus Advisors offers comprehensive Owner’s Technical Representation (OTR) services, acting as the owner's advocate throughout the project lifecycle. Their responsibilities encompass:
-
Visioning & Guiding Principles: Collaborating with project owners to define the project's purpose and establish guiding principles for success.
-
Stakeholder Engagement & Collaboration: Ensuring effective communication and collaboration among all stakeholders to achieve project objectives.
-
Capital Program Management: Efficiently managing capital programs to optimize resource utilization and ensure timely project delivery.
-
Delivery Method Consulting: Advising on the most suitable project delivery methods to meet specific project needs.
-
Risk Evaluation & Mitigation: Identifying potential risks and implementing strategies to mitigate them, safeguarding project success.
-
Construction Process & Delivery Management: Overseeing construction processes to maintain project timelines and quality standards.
-
Construction Consulting: Providing expert advice throughout the construction phase to address challenges and ensure project goals are met.
-
FFE Procurement: Managing the procurement of furniture, fixtures, and equipment to align with project specifications and budgets.
These services are designed to keep projects on schedule, within budget, and aligned with the owner's goals, providing peace of mind throughout the construction process.
Leadership & Regional Presence
The Veridus Group was founded in 2011 by Tim Jensen, who has served as the Owner’s Representative on over $1 billion of public and private work. The Owner’s Technical Representation division is led by David Rainey, Vice President, who brings extensive experience in building assessments and civil design.
In Michigan, Landon Martin serves as the Director for Veridus Advisors, bringing a background in construction and affordable housing. The Michigan team has been actively involved in regional projects, such as the $110 million bond program for Mattawan Consolidated School District, where they provided Owner’s Representation services.
Landon Martin
Katie Jacobs
Jon Ackley-Jelinek
NEW UPDATES
Batter Up! ⚾🧢🥎
The upcoming improvement project for the baseball and softball fields will focus on enhancing safety, accessibility, and overall field quality. The project includes the installation of new fencing and backstops for both fields to match the updated fencing planned for the football stadium. Emergency vehicle access points will also be added to both fields.
Upgrades will include new irrigation systems and a modernized controller for better zone management. Since the bladder tanks were replaced two years ago, they will remain in place. On the baseball field, the infield will be re-sodded and the area between third base and home plate will be leveled. Both outfields are currently in good condition and do not require regrading or reseeding.
Additional improvements include the installation of new foul line markers on both fields and cement pads in front of each dugout, extending from the dugout entrances to the safety fences. Finally, the batting cages for both baseball and softball will be updated, with consideration given to relocating the softball cages to avoid conflict with the new access road leading to the team room.
Middle & High Schools to Receive Updated Furniture
Planning for the replacement of student and teacher furniture in both the middle and high schools is well underway, funded by the school construction bond. To ensure the best selection, teams have visited multiple industry-leading furniture suppliers, touring showcase rooms to evaluate modern, functional options that will enhance the learning environment. Several debrief meetings have taken place to discuss findings and narrow down potential suppliers. The next step in the process will involve selected suppliers presenting their equipment to building staff, who will have the opportunity to pilot it this fall and provide feedback. Much of the existing furniture is over 25 years old, and the new selections will usher in updated, modern environments for both students and staff, fostering a more comfortable and engaging learning experience.
The Month of May brings the organization of staff groups to review our chosen furniture partners and plan out the pilot schedule for this coming fall!
ON-GOING PROJECTS 📆
BID PACKAGE 1A - STADIUM WORK
Week 7
Significant sitework progress was made this period. The track asphalt was fully removed, and the area was graded and compacted in preparation for upcoming testing and evaluation. Storm piping installation was completed from the South Retention Basin up to manhole MH-3. On the north end, rough grading of the pond was finished, making it ready for landscaping. Additionally, the visitor bleacher stairs were removed to allow for necessary modifications.
Manhole Installation
Southwestern Tree Line
Storm Piping Southwest Property
Week 8
Site work is progressing steadily. The track fill is nearly complete, with testing successfully passed, and demolition work inside the stadium is finished. Crews continue excavation of the stormwater retention pond.
Looking ahead to next week, efforts will focus on completing excavation of the south pond, finishing the track fill, beginning installation of storm infrastructure around the field, and finalizing pricing for Bulletin 2 in preparation for Board approval.
HIGH SCHOOL FIRE ALARM UPDATE Bid Package 1D⚡🔥
Weeks 1 & 2
As of the week of April 4, 2025, work progressed steadily with conduit pulling activities beginning across the site. Efforts were concentrated in the Science Lab, where initial work got underway. Cabling and rough-ins also commenced in Unit G, marking a key step forward in that area. Simultaneously, crews continued to assess and review existing site conditions to inform ongoing work.
During the week of April 11, 2025, most of the work remained focused on Unit G. Crews pulled wire throughout the Science Labs and began running conduit and piping beneath the Auditorium seating. Additional tasks included drilling above doorways and classrooms to prepare for sleeve installation. Rework also continued for the independent sleeves intended for wire runs. In the adjacent hallway leading to Unit G, wire pulling progressed steadily toward the connected classrooms.
Weeks 3 & 4
By the week of April 17, 2025, significant strides were made in electrical infrastructure. Conduits were run from the electrical panels to newly installed junction boxes designated for new devices. In the gym hallway, workers began installing device boxes within the ceiling tiles. Wire was pulled throughout the locker rooms and into individual locker areas. Additionally, new fire alarm wiring continued to be routed from hallways into the classrooms.
During the week of April 25, 2025, the team began work in the Gymnasium, running conduit and installing boxes as part of the ongoing upgrades. Efforts also continued in the second-floor corridor ceiling, where crews installed additional boxes and extended cabling runs. In the Locker Room, conduit and box installation began as well, using surface-mounted setups as a temporary solution ahead of the future BP3 renovations.
Stadium Conceptual Design
Stadium Construction Phases
Stadium Work, Phase 2 Summer 2026
It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026 and will include renovations to the current press box and the addition of a new sound system.
Stadium Work, Phase 3
Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvements to the current entryway on the North side of the stadium.
BID PACKAGE 2A PLANNING UNDERWAY
Bold Designs for New Maintenance and Transportation Complex
Exciting progress is underway as we move forward with the design of a new Transportation and Maintenance Building, which is set to begin construction this fall! Located just west of the current high school, this much-needed facility will replace outdated and undersized buildings that no longer meet modern safety standards.
Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker and shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.
This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.
ARCHIVED INFORMATION
Construction Bid Packages Explained
Construction Bid Packages Exlplained
The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.
Please note: The bid packages listed below are currently in various stages of design. Additional bid packages, including those for field turf, the middle school cafeteria, technology, the natatorium, and others, have not yet entered the design phase but will be developed and updated in the future.
Bid Package 1A - Stadium Inner Scope
- Replace field with turf
- Replace track & field
- Replace inner perimeter fencing
- Fall 2024 - project design
- Winter 2024 - project bidding
- Spring 2025 - project construction
Bid Package 1B - Campus Traffic Flow & Parking
- High School and Middle School parent carpool loop reworked
- Separation of buses from carpool/community traffic
- Expanded parking in front of the middle and high school
- Stadium press box renovations
- Spring 2026 - project bidding
- Summer of 2026 - project construction
Bid Package 1C - Baseball & Softball Field Upgrades
- Update irrigation system
- Updated perimeter fencing
- Spring 2025 - project bidding
- Summer 2025 - construction
Bid Package 1D - Middle/High School Fire Alarm System Replacement
- Winter 2025 - project bidding
- Summer 2025 - construction
Bid Package 2A - New Construction Transportation & Maintenance Facility
- Winter 2025 - Design Development
- Summer 2025 - project bidding
- Fall 2025 - Fall of 2026 - construction
Our Plan. Our Students. Our Future.
Our focus revolves around five key objectives for the bond:
- Preserve existing assets
- Prioritize safety and security
- Provide future-focused academic and extracurricular experiences for our students
- Enhance infrastructure
- Demonstrate fiscal responsibility
Safety & Security:
- Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
- Replacement of outdated, unreliable security equipment at each building
Transportation:
- Continued replacement of an aging bus fleet
Academic Learning Spaces + Experience:
- Replacement of original, aged classroom equipment and furniture at middle and high schools
- Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.
Fine Arts:
- Upgrades to lighting and media equipment at the high school auditorium
Infrastructure:
- Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
- Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
- Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
- Addition of cooling to main gymnasiums at the high school
Student Athletic Experience:
- Renovation of aged high school locker rooms
- Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
- New high school track - the current track is backwards and nearly unusable in the current condition
- Upgrades to baseball and softball fields
- Construction of a new multi-use turf field (soccer, lacrosse, football)
- Maintenance of existing practice fields; addition of a new outdoor practice space
Other Construction:
- Addressing overcrowding in the current Middle School cafeteria
- Replacement of aged, quickly deteriorating tennis courts
- Replacement of aged transportation building and maintenance building
- Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
- Construction of a student/community pool