Lake ES -School Replacement Project
May 2025

Project Updates - May 2025
Construction Activity
Building E and F (Kindergarten Wings)
- Completed the gypsum board tape, finish, and stucco finish coat
- Removed the scaffold
- Continuation of installing the electrical, HVAC, and plumbing
- Begin the painting and tile installation in restrooms, and install the ceiling grid
Building D (Cafeteria)
- Completed rough framing and acoustical metal deck
- Continuation of installation of mechanical, electrical, plumbing, roofing, gypsum board tape, and plaster finish.
Project Overview
Project Scope: The primary purpose of this project is to replace the school campus. The campus will be occupied during the duration of this project. This project is an investment in our community through the use of taxpayer bond dollars.
Anticipated Completion: Fall 2025
The project has two main construction phases. The project design started in August 2021. The first phase of construction included new buildings and site work on the East half of the campus and was completed in Fall 2024. The second phase will include new buildings and remaining site work on the West half of the campus, scheduled through Fall 2025.
Anticipated Completion: Fall 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Outdoor Dining Canopy Structure
Building E (Kinder) and Building D (Cafeteria)
Final Stucco Coat on building E and rough coat on building D