Collins ES Critical Needs Project
August 2023

Project Updates - August 2023
Summer Work - Site
Welcome Back! While there has been construction in the parking lots over the summer, they will be reopened for the first day of school. Additional striping will be completed after school begins.
Construction Completed Last Month
- Installation of accessible classroom sinks and casework
- Installation of accessible restrooms in the kindergarten classroom
- Replacement of classroom door hardware
- Installation of the HVAC cabinets and mechanical ductwork in the classrooms
Upcoming Activities
- Finishing installation of the refrigerant piping on the classroom hallway roofs. Safety measures will remain in place while work is performed on the rooftop.
- Additional equipment is scheduled to be delivered in October and December. This equipment will be installed outside and will not affect classroom operation.
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Spring 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Kindergarten
Accessible restroom being painted.
Staffing Parking Lot
Formwork for new main switchboard (MSB) equipment pad