BOND UPDATE
August 28, 2026
🌟BACK TO SCHOOL EDITION🌟
BUS LANE/TRAFFIC FLOW UPDATE🚍🚗🚜
Recent progress includes continued irrigation and landscaping, installation of sod around the retention pond, stair railings, and speed bumps. The arm gates at the bus loop and fire lane are now programmed and operational, and owner training has been completed. Striping and signage work are also ongoing.
🙌We also greatly appreciate the care, patience, and attention our parents, students, and staff have shown during the first week of driving with the new traffic configuration.🥰 Overall, the transition has gone very smoothly, with very few issues as everyone adjusts to the new patterns.
This week, crews continued irrigation and landscaping work and focused on additional site cleanup.
Pictured left: tractors.
Pictured Below: behind middle and high school.
VLOG: Parent & Carpool Traffic
Pictured below: new trees being planted behind the Middle School. All in, we are scheduled to plant over 100 new trees during the Middle School project (bus lane and new office/parking lot, North).
VLOG: Tour the Bus Lanes
Pictured below: new landscaping West of the tennis courts.
TRANSPRT. & MAINT. BLDG. UPDATE 🔨🔧
Recent progress includes continued drywall finishing and interior liner panel installation, along with temporary doors installed at the administration area. Condensing units and condensate lines have been installed, and fine grading is underway in preparation for asphalt.
This week, crews installed the base course asphalt Monday through Wednesday, continuing drywall and liner panel work, advancing MEP rough-ins, and installing the final overhead door.
Pictured below: drywall installation.
Pictured below: various interior views.
VLOG: Check out the pavement at the M&T Facility!
BID PACKAGE 4 - NEW TENNIS 12 COURTS 🎾🥇
Site preparation is underway for the next phase of improvements near the tennis courts and field events - shotput and discus - area. Over the past two weeks, crews have been clearing trees and brush along the project area and property line, followed by stripping and removing topsoil to prepare the site for upcoming construction.
The most recent work, shown in the photos, includes continued topsoil removal throughout the tennis court and surrounding project areas. These early site-preparation activities are an important first step as the area is cleared, graded, and readied for the new improvements.
AS A REMINDER, part of the bond campaign is to be intentional about tree replacement. It will not necessarily be a one-to-one program, but the team is committed to replanting as many varieties of tree as able. For example, in the middle school project alone (new offices and parking out front), we are tentatively scheduled to plant over 100 trees throughout the North side of campus.
GENERAL TIMELINE - SUBJECT TO CHANGE
The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.
2024
Summer 2024
✅COMPLETE Owner Direct – Replace Existing Soccer Lights
✅COMPLETE Owner Direct – Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)
Fall 2024
✅COMPLETE Owner Direct – Student Device Replacement Phase 1
Winter 2025
✅COMPLETE Owner Direct – Student Device Replacement Phase 2
2025
March – August 2025
✅COMPLETE - Bid Package 1A – Football Stadium: Inner Scope
Summer 2025
✅COMPLETE- Bid Package 1C – Baseball & Softball Field Improvements
✅COMPLETE Bid Package 1D – HS Replace Fire Alarm System
✅COMPLETE Bid Package 1E – HS Carpet Replacement
Fall 2025
✅FINISHING - Bid Package 1F – HS Gymnasium Cooling
✅COMPLETE-Band Shell; future - pit section, lighting, stage floor, A/V, curtain) )
Nov 2025 – Oct 2026
✅UNDERWAY Bid Package 2 – Transportation & Maintenance Facility
2026
March – September 2026
✅FINISHING - Bid Package 1B – Campus Traffic Flow Phase 1
Sept 2026 – March 2028
✅DESIGN PHASE UNDERWAY - Bid Package 4 – Field House
✅DESIGN PHASE UNDERWAY - Bid Package 4 – Natatorium
✅COMPLETE - Middle and High School Classroom Furniture
✅COMPLETE - Phase 2 Stadium, sound system replacement, press box repainting/new sign; access/emergency road
Upcoming
- Middle School Office Expansion: 2026-2027
- Middle School Cafeteria Renovation: 2027-2028
- High School Weight Room Renovation: 2027-2028
- Natatorium/Fieldhouse/Multipurpose Field: 2027-2028
- Middle School Science Lab and Toilet Room Renovation: 2028-2029