Smore logo
remove_red_eye 5.1K
page background
Logo

BOND UPDATE

August 28, 2026

BOND UPDATE August 28, 2026
BOND UPDATEAugust 28, 2026

🌟BACK TO SCHOOL EDITION🌟 🌟BACK TO SCHOOL EDITION🌟

BUS LANE/TRAFFIC FLOW UPDATE🚍🚗🚜 BUS LANE/TRAFFIC FLOW UPDATE🚍🚗🚜

User uploaded image
zoom_out_map

Recent progress includes continued irrigation and landscaping, installation of sod around the retention pond, stair railings, and speed bumps. The arm gates at the bus loop and fire lane are now programmed and operational, and owner training has been completed. Striping and signage work are also ongoing.


🙌We also greatly appreciate the care, patience, and attention our parents, students, and staff have shown during the first week of driving with the new traffic configuration.🥰 Overall, the transition has gone very smoothly, with very few issues as everyone adjusts to the new patterns.

User uploaded image
zoom_out_map

This week, crews continued irrigation and landscaping work and focused on additional site cleanup.


Pictured left: tractors.


Pictured Below: behind middle and high school.

User uploaded image
zoom_out_map Show in original size

VLOG: Parent & Carpool Traffic VLOG: Parent & Carpool Traffic

Mattawan Minute! Take a Drive with Mr. Fleenor

Pictured below: new trees being planted behind the Middle School. All in, we are scheduled to plant over 100 new trees during the Middle School project (bus lane and new office/parking lot, North).

User uploaded image
zoom_out_map Show in original size

VLOG: Tour the Bus Lanes VLOG: Tour the Bus Lanes

Mattawan Minute - Take a drive on the new bus lane!

Pictured below: new landscaping West of the tennis courts.

User uploaded image
zoom_out_map Show in original size

TRANSPRT. & MAINT. BLDG. UPDATE 🔨🔧 TRANSPRT. & MAINT. BLDG. UPDATE 🔨🔧

User uploaded image
zoom_out_map

Recent progress includes continued drywall finishing and interior liner panel installation, along with temporary doors installed at the administration area. Condensing units and condensate lines have been installed, and fine grading is underway in preparation for asphalt.


This week, crews installed the base course asphalt Monday through Wednesday, continuing drywall and liner panel work, advancing MEP rough-ins, and installing the final overhead door.


Pictured below: drywall installation.

User uploaded image
zoom_out_map Show in original size

Pictured below: various interior views.

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

VLOG: Check out the pavement at the M&T Facility! VLOG: Check out the pavement at the M&T Facility!

Transportation and Maintenance Facility Update
User uploaded image
zoom_out_map Show in original size

BID PACKAGE 4 - NEW TENNIS 12 COURTS 🎾🥇 BID PACKAGE 4 - NEW TENNIS 12 COURTS 🎾🥇

Site preparation is underway for the next phase of improvements near the tennis courts and field events - shotput and discus - area. Over the past two weeks, crews have been clearing trees and brush along the project area and property line, followed by stripping and removing topsoil to prepare the site for upcoming construction.


The most recent work, shown in the photos, includes continued topsoil removal throughout the tennis court and surrounding project areas. These early site-preparation activities are an important first step as the area is cleared, graded, and readied for the new improvements.


AS A REMINDER, part of the bond campaign is to be intentional about tree replacement. It will not necessarily be a one-to-one program, but the team is committed to replanting as many varieties of tree as able. For example, in the middle school project alone (new offices and parking out front), we are tentatively scheduled to plant over 100 trees throughout the North side of campus.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

GENERAL TIMELINE - SUBJECT TO CHANGE GENERAL TIMELINE - SUBJECT TO CHANGE

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


2024

  • Summer 2024

    • ✅COMPLETE Owner Direct – Replace Existing Soccer Lights

    • ✅COMPLETE Owner Direct – Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)

  • Fall 2024

    • ✅COMPLETE Owner Direct – Student Device Replacement Phase 1


Winter 2025

  • ✅COMPLETE Owner Direct – Student Device Replacement Phase 2


2025

  • March – August 2025

    • ✅COMPLETE - Bid Package 1A – Football Stadium: Inner Scope

  • Summer 2025

    • ✅COMPLETE- Bid Package 1C – Baseball & Softball Field Improvements

    • ✅COMPLETE Bid Package 1D – HS Replace Fire Alarm System

    • ✅COMPLETE Bid Package 1E – HS Carpet Replacement

  • Fall 2025

    • ✅FINISHING - Bid Package 1F – HS Gymnasium Cooling

    • ✅COMPLETE-Band Shell; future - pit section, lighting, stage floor, A/V, curtain) )

  • Nov 2025 – Oct 2026

    • ✅UNDERWAY Bid Package 2 – Transportation & Maintenance Facility


2026

  • March – September 2026

    • ✅FINISHING - Bid Package 1B – Campus Traffic Flow Phase 1

  • Sept 2026 – March 2028

    • ✅DESIGN PHASE UNDERWAY - Bid Package 4 – Field House

    • ✅DESIGN PHASE UNDERWAY - Bid Package 4 – Natatorium

  • ✅COMPLETE - Middle and High School Classroom Furniture

  • ✅COMPLETE - Phase 2 Stadium, sound system replacement, press box repainting/new sign; access/emergency road


Upcoming


  • Middle School Office Expansion: 2026-2027
  • Middle School Cafeteria Renovation: 2027-2028
  • High School Weight Room Renovation: 2027-2028
  • Natatorium/Fieldhouse/Multipurpose Field: 2027-2028
  • Middle School Science Lab and Toilet Room Renovation: 2028-2029
User uploaded image
zoom_out_map Show in original size
Bond 2024 Website
General Bond 2024 Information
Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter