SHANNON ES - MPR Project
June 2026

Project Updates - June 2026
Activities This Month
- Started up and tested new kitchen equipment.
- Develop a punch list for site work and the kitchen
- Health department inspection for the kitchen
- Asphalt paving at the new utility yard
- PG&E Inspection for the new electrical service
- Paint trash enclosure gates
- Drinking Fountain
- Demolish the existing cafeteria
- Start site work activities
Activities Next Month
- Asphalt and concrete paving. Ashalt sealcoat and striping.
- Landscaping
- PG&E power shut down and new PG&E service.
- Final electrical connections and switch over to new service.
- Test electrical systems
- Test all systems in the new kitchen with all required power available.
- Finalize punchlists for the kitchen and cafeteria.
- Prepare for project closeout
Project Overview
Project Scope: This project will include the construction of a new multipurpose building featuring a dining area, stage, food services kitchen, serving areas, and support spaces—an investment in our community using taxpayer-funded bond dollars.
Upon completion, the existing portable cafeteria will be removed. The project also includes roll-up doors for exterior access, surrounding landscaping, and infrastructure for a new garden.
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net