RHS Modernization Project
February 2026

February 2026 - Construction Update
Activities This Month
The former south side parking lot solar panels have been successfully demolished.
We have also excavated the sewer line to accommodate new site infrastructure improvements.
We are currently working on installing a new fire-water line across the site that ties into the existing loop of fire water line.
On the northwest side of the site, we continue and advance installation of the storm drain system.
Activities Next Month
We will be installing the new domestic water line along the west side of the site and tying it into the existing water meter.
We plan to get the new classroom building pad certified to start foundation work.
We will complete the storm drain system.
Project Overview
The Richmond High School Modernization project involves demolishing a portion of the classroom building to make way for a new two-story building along 23rd Street. The remaining classroom section will be updated, including the installation of new windows. The large gym and the 600 Buildings will receive a refresh.