Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
Renaissance @ Rand
Project Status: September 26, 2025
Project Completion: 38% complete
Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th
Contract to Date: $3,785,100.00
Paid to Date: $0.00
George Inness
Project Status: September 26, 2025
Project Completion: 38% complete.
Current Status: Burners are currently being installed. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th
Bradford Elementary
Project Status: September 26, 2025
Project Completion: 35% complete.
Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th
Watchung Elementary
Project Status: September 26, 2025
Project Completion: 38% complete.
Current Status: Burners are currently being installed. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th
Edgemont Elementary
Project Status: September 26, 2025
Project Completion: 35% complete.
Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th
Northeast Elementary
Project Status: September 26, 2025
Project Completion: 40% complete.
Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.
Upcoming Milestones: Rear Dampers to be shipped out on October 10th