Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

Renaissance @ Rand Renaissance @ Rand

Project Status: September 26, 2025

Project Completion: 38% complete

Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

Contract to Date: $3,785,100.00
Paid to Date: $0.00

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: September 26, 2025

Project Completion: 38% complete.

Current Status: Burners are currently being installed. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Bradford Elementary Bradford Elementary

Project Status: September 26, 2025

Project Completion: 35% complete.

Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Watchung Elementary Watchung Elementary

Project Status: September 26, 2025

Project Completion: 38% complete.

Current Status: Burners are currently being installed. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Edgemont Elementary Edgemont Elementary

Project Status: September 26, 2025

Project Completion: 35% complete.

Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Northeast Elementary Northeast Elementary

Project Status: September 26, 2025

Project Completion: 40% complete.

Current Status: Burners are currently onsite. Schools to begin test-firing existing boilers to make sure there is heat for winter season.

Upcoming Milestones: Rear Dampers to be shipped out on October 10th

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter