Lake ES -School Replacement Project
August 2025

Project Updates - August 2025
New Entry Points for Fall 2025
See the diagram below
Construction Activity
Building E and F (Kindergarten Wings)
These buildings will OPEN in time for the first day of school!
- Finishing the rooms for opening
- Installing the kindergarten play structures
Building D (Cafeteria)
- Next month will include installing fire alarm and sprinkler systems and finishing the floors
- This building and the main playground will be completed and opened later in the fall
Project Overview
Project Scope: The primary purpose of this project is to replace the school campus. The campus will be occupied during the duration of this project. This project is an investment in our community through the use of taxpayer bond dollars.
Anticipated Completion: Fall 2025
The project has two main construction phases. The project design started in August 2021. The first phase of construction included new buildings and site work on the East half of the campus and was completed in Fall 2024. The second phase will include new buildings and remaining site work on the West half of the campus, scheduled through Fall 2025.
Anticipated Completion: Fall 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net